Quantity take-off, measurement, variations: BoQ quantities

Glossary with rules from the German VOB/B (dejure.org) and BGB (gesetze-im-internet.de) and terms based on German Wikipedia. Scalera information comes from the product matching page and the FAQ.

Abstract illustration: a construction drawing with a tape measure, a grid with measured areas and an extra item sheet with a plus sign.
Introduction
Quantity take-off calculates quantities from drawings or measurements, site measurement records the work actually done, and a variation covers changed or additional work with new pay.

30

days without agreement on a change, after which the client may order it in text form (Section 650b BGB)

10 %

maximum quantity deviation for which the agreed unit price stays valid under VOB (VOB/B Section 2(3))

2.5 m²

single size: only larger openings are deducted when concrete is billed by area (Wikipedia on DIN 18331)

X31

GAEB exchange file for quantity calculation, available since October 2013 (Wikipedia)

As of 24 Nov 2026. Resource type: glossary. Legal rules from VOB/B and BGB (Germany), terms based on German Wikipedia; sources are linked directly. This article is not legal advice.

In short

  • Quantity take-off calculates the quantity for each item, from drawings or a site measurement, under the measurement rules of each trade.
  • Site measurement records what was actually built. Under a VOB contract it should be done jointly with the client where possible.
  • Variation is the changed or additional work together with new pay. The variation quote states the price for it.

Sources: VOB/B Sections 1, 2, 14 (dejure.org), BGB Sections 650b, 650c (gesetze-im-internet.de), Wikipedia, retrieved 24 Nov 2026.

Three terms, three points in time

The three terms describe the same thing, the quantity of work, at different points in time. Before the tender it is calculated, during and after execution it is measured, and if the work changes it is renegotiated. How a BoQ item is structured and where the quantity sits is explained in the glossary short text, long text, item number.

Quantities across the project
TermWhenResult
Quantity take-offbefore award and at billingquantity per item
Site measurementduring and after worksrecorded work
Variationon changenew item, new price

Sources: Wikipedia, Aufmass, VOB/B Section 14, VOB/B Section 2.

Quantity take-off: how the quantity gets into the BoQ

For a BoQ, the scope of work is derived from construction drawings or measured on site; the quantity calculation built on it is also called Massenermittlung in German site language (Wikipedia). Which area or length counts is set by section 5 of each standard in VOB Part C, i.e. DIN 18299 ff., separately for each trade.

An example from the concrete standard DIN 18331: when billing by area, only openings larger than 2.5 m² each are deducted, so a normal door opening in a concrete wall is measured as if it were wall (Wikipedia). The BoQ quantity therefore follows the measurement rule, not the material actually installed. For your quote this means you calculate order quantity, offcuts and packaging unit separately. How to convert BoQ units into order units is shown in converting units of measure.

Site measurement: what was really built

Under a VOB unit-price contract, billing is based on the contract unit prices and the work actually performed (VOB/B Section 2(2)). The findings needed for this should be made jointly where possible and as the work progresses; for work that will be hard to check later, the contractor requests a joint finding in good time (VOB/B Section 14(2)).

The invoice includes the quantity calculations, drawings and supporting documents, and contract changes must be clearly marked in it (VOB/B Section 14(1)). Electronic billing uses REB 23.003 with the DA11 interface or the GAEB file X31 (Wikipedia). In Austria, ÖNORM A 2063 describes data exchange including billing; in Switzerland, the contractor attaches a measurement to every interim payment under SIA Art. 144 (Wikipedia). What happens to the unit price when quantities deviate significantly is explained in the glossary unit price, total price, lump sum.

Variation: when the work changes

Under VOB/B the client may order changes to the design, and the contractor must carry out work that was not agreed but is required, if the client asks (VOB/B Section 1(3) and (4)). If this changes the basis of the price, a new price must be agreed, if possible before execution. Additional work gives a right to special pay; the contractor must announce this claim before starting the work (VOB/B Section 2(5) and (6)).

In a BGB construction contract, the parties aim to agree on the change and on the additional or reduced pay; the contractor prepares an offer for it, the variation quote (Section 650b(1) BGB). Without agreement within 30 days, the client may order the change in text form (Section 650b(2) BGB). Pay is then based on the costs actually required plus reasonable surcharges for general overheads, risk and profit (Section 650c(1) BGB).

According to Wikipedia, variation management covers pay variations as well as disruption claims and damages (Wikipedia, Nachtragsmanagement). New or changed items with a price arise from pay variations; that case is the focus below.

What this means for manufacturers and distributors

The rules in VOB/B and BGB concern the contract between client and contractor. Whether and how they apply to your supply contract depends on what you agreed. Their effects still reach you: if a BoQ quantity rises or an item is added, the contractor needs a price for the variation quote, and the agreement should be in place before execution where possible (VOB/B Section 2(5)).

A variation does not always arrive in the same email thread as the original request. How to recognise it anyway and assign it to the project is described in capturing tender requests from the email inbox.

The BoQ quantity is a billing figure, not an order quantity.

Checklist: quantities and variations in your quote

  1. Record the quantity basis: take over BoQ quantity, unit and item number for each item unchanged.
  2. Calculate order quantity separately: show offcuts, packaging unit and openings measured as wall on their own.
  3. Clarify price validity: state which quantities your price applies to and how you handle more or less quantity.
  4. Assign variations: carry the project and item numbers of the original request, mark new items.
  5. Derive variation prices: start from the original quote and justify deviations so the contractor can pass them on.

What Scalera takes on

Scalera processes tender documents and BoQs in PDF, scan, Excel, GAEB, NPK, ÖNORM and other standards, extracts the items and matches each one to products from your catalogue (product matching). For this, a variation BoQ is a BoQ like any other.

If a conversion factor is set in your product data, Scalera converts units of measure automatically; otherwise it notifies you (FAQ). Requests without a separate document are recognised directly in the email text, including quantities and units where available (FAQ). Site measurement and variation review stay with the contractor and site management. Bring your own BoQ to the demo.

Frequently asked questions

What is the difference between site measurement and quantity take-off?

Site measurement (Aufmass) records the extent of the work on site or from construction drawings. Quantity take-off (Mengenermittlung) builds on it and calculates the billable quantities under the measurement rules of VOB Part C (Wikipedia, Aufmass).

Who carries out the site measurement?

Under a VOB contract, contractor and client should make the findings needed for billing jointly where possible and as the work progresses (VOB/B Section 14(2)).

What is a variation quote?

The contractor's offer for the additional or reduced pay for changed work. Under Section 650b BGB the contractor must prepare it when the client requests a change; for a change to the agreed result only if the work is reasonable for the contractor (Section 650b BGB).

What happens if the parties do not agree on a variation?

If there is no agreement within 30 days of receiving the change request, the client may order the change in text form (Section 650b(2) BGB). Pay is then based on the costs actually required plus reasonable surcharges (Section 650c BGB).

Does Scalera read quantities from requests?

Yes. Scalera extracts the items from BoQs and matches them to products (product matching); for requests in the email text it also extracts quantities and units where available. If a conversion factor is set, Scalera converts units (FAQ).