In short
- An outlier is a price that differs clearly from the other quotes for the same line item, either lower or higher.
- Compare every line item with the median of the quotes. A single extreme value distorts the median less than the average.
- Public clients have to clarify abnormally low prices (Section 60 VgV, Section 137 BVergG 2018, Art. 38 PPA).
- A very low price on a line item with an uncertain quantity can turn the lowest total into the highest later on.
As of 24 Nov 2026. Legal texts checked on gesetze-im-internet.de, lxgesetze.de, ris.bka.gv.at and fedlex.admin.ch. Not legal advice.
What is an outlier in a bid tabulation?
An outlier is a price that differs clearly from the other quotes for the same line item. It can be lower or higher. How a bid tabulation is built and why you compare line by line is explained in the guide to bid comparison.
The level matters. A total can look normal even though single line items deviate strongly, because low and high prices cancel each other out. So you check the line items first and the total second.
How do you find outliers line by line?
For each line item you only need two values: the median of all quotes and each quote's deviation from it in percent. The median is the middle value when you sort the prices by size. Here is how:
- Align units and quantities before you calculate.
- Work out the median unit price for each line item.
- Calculate each quote's deviation from the median in percent.
- Set a review threshold and flag every line item above it.
- Sort the flagged items by impact: quantity times price difference.
The legal texts cited here set no fixed threshold. You choose it for your comparison, and it applies equally to all quotes. Aligning scope and units first is called bid leveling; the side-by-side table itself is the bid tabulation. If prices come in different units, see the article on converting units of measure.
| Line item | Median | Unusual |
|---|---|---|
| 1.1 Wall, 1,200 m² | €48 | none |
| 1.2 Joint, 300 m | €10 | none |
| 1.3 Opening, 40 pcs | €85 | C: €18 (−79%) |
| 1.4 Extra, 200 m² | €7 | C: €25 (+257%) |
Made-up figures. Quote A: €48/9/85/6, B: €52/11/90/7, C: €46/10/18/25. Median = middle of the three values.
Why the median and not the average?
A single extreme price pulls the average along with it. For line item 1.3 the average of the three quotes is €64.33, the median €85. Against the average, quote C looks less unusual than it is.
What can sit behind an unusual price?
An outlier is a question first, not a verdict. These causes are possible:
- Misread: unit, quantity or price basis differs from the bill of quantities, for example piece instead of pack.
- Different scope: the quote covers less, or a different product, than requested.
- Shifted: the costs of this item sit in another line item.
- Arithmetic error: quantity times unit price does not give the line total.
- Genuine advantage: a cheaper method, a different technical solution or special conditions on the supplier's side.
The last cause is expressly provided for: Section 60 VgV lists the economics of the method, technical solutions and exceptionally favourable conditions as review points. A low price can therefore be justified. If discounts, early-payment terms or freight are the reason, see discounts, early payment, freight.
A simple plausibility test comes from Austrian law: is the unit price for a higher-value item higher than for a lower-value one (Section 137(3) BVergG 2018)? If not, it is worth asking.
Why can a low price become expensive later?
In the example above, quote C has the lowest total. But it has a very low price on line item 1.3 and a very high one on the extra item 1.4. If the quantity of the extra item rises from 200 to 600 m² during construction, the ranking changes:
| Quote | BoQ quantity | Extra at 600 m² |
|---|---|---|
| A | €64,900 | €67,300 |
| B | €70,700 | €73,500 |
| C | €63,920 | €73,920 |
Made-up figures from the table above. Only line item 1.4 changes; all other quantities stay the same.
The lowest quote becomes the highest. So for every line item with an uncertain quantity, check how sensitive the total is. When a unit price may change after a quantity deviation is explained in the glossary unit price, lump sum, total price.
A price nobody can explain is not an advantage. It is an open risk in the comparison.
What do procurement rules in DE, AT and CH require?
In procurements under the German Procurement Ordinance, the public client asks for an explanation if the price or cost looks abnormally low in relation to the work. If the low level cannot be satisfactorily explained, the client should reject the tender (Section 60 VgV). For construction work under Section 1 of VOB/A, no contract may be awarded to a tender with an unreasonably high or low price (Section 16d(1) VOB/A).
In Austria, the client must ask for an explanation and carry out an in-depth review if the total price is abnormally low, key line items have unit prices that are too high or too low, or there are well-founded doubts (Section 137 BVergG 2018). The client may only exclude the tender if, despite the explanation, the prices cannot be explained in business terms (Section 138(5) BVergG 2018).
In Switzerland, the federal contracting authority must make appropriate enquiries if a total price looks abnormally low compared with the other tenders (Art. 38(3) PPA). What bidders disclose in that situation is covered in the article on construction tender pricing.
| Country | Trigger | Result |
|---|---|---|
| Germany | price abnormally low | explanation, else no award |
| Austria | total or unit prices | in-depth review |
| Switzerland, federal | total abnormally low | enquiries |
Sources: Section 60 VgV, Section 16d VOB/A, Section 137 BVergG 2018, Section 138 BVergG 2018, Art. 38 PPA. Cantons and other countries have their own rules.
How do you clarify an unusual price?
Ask in writing and specifically, line item by line item. Request an answer by a deadline so your comparison does not stall. These four questions cover the causes above:
- Does the price refer to the unit and quantity in the bill of quantities?
- Is the full scope included, and which product is offered?
- Are costs of this item included in another line item?
- Which conditions or methods make the price possible?
Record the question and the answer. Public clients document clarifications too: under VOB/A in text form (Section 15(1) VOB/A), at Swiss federal level in writing (Art. 38(2) PPA). In public tenders under VOB/A the rule is: clarify yes, negotiate on price generally no (Section 15(3) VOB/A).
What if your own quote is the outlier?
As a manufacturer, distributor or subcontractor you may be the outlier yourself. A low price is not a mistake if you can explain it. So keep your price build-up ready to answer a query within the deadline.
If a bidder lets a set deadline for clarification pass, the tender is excluded under VOB/A (Section 15(2) VOB/A). How scoring and weighting decide the award is explained in the guide award criteria in construction.
Where does software help and what does your team decide?
Scalera reads incoming quotes and lines them up along your bill of quantities, line by line. Gaps stand out immediately, and suppliers who have not replied get an automatic reminder (quote comparison). Before that, requests go out to matching manufacturers and subcontractors with the same line-item overview (Supplier Matching).
That gives you a complete basis without retyping. Which deviation to query, which explanation to accept and who gets the contract is your team's decision.
Frequently asked questions
When is a price abnormally low?
Neither Section 60 VgV nor Section 16d VOB/A nor Art. 38 of the Swiss PPA sets a fixed percentage. The comparison is with the work itself (Section 60 VgV), with the other tenders (Art. 38(3) PPA) or with past experience and market conditions (Section 137(1) BVergG 2018). So you set your own review threshold and record it in writing.
What is a speculative unit price?
It is a unit rate set deliberately very low or very high because the bidder expects a different quantity than the bill of quantities states. If the quantity changes, the total shifts in the bidder's favour. The worked example above shows how this can flip the ranking.
Can a public client negotiate on price?
In tenders under VOB/A, negotiations about changes to tenders or prices are generally not permitted (Section 15(3) VOB/A). In Switzerland, a request to adjust prices is only allowed as part of a tender clarification round (Art. 39 PPA). Asking for an explanation, by contrast, is allowed and sometimes required.
What happens with arithmetic errors in a tender?
In Germany, the unit price prevails if a line total does not match quantity times unit price (Section 16c(2) VOB/A). In Switzerland, the contracting authority corrects obvious arithmetic errors ex officio (Art. 38(1) PPA). Austria has a 2 % threshold if the tender documents set it (Section 138(7) BVergG 2018).
Do these rules apply to private clients and general contractors?
No. VgV, VOB/A, BVergG and the Swiss PPA govern public contracting authorities. If you compare quotes from suppliers or subcontractors privately, you can use the same logic: spot the deviation, ask in writing, document the answer.
How many quotes do I need for a meaningful comparison?
From three quotes onwards there is a real median, a middle value. With two quotes the comparison only shows that they differ, not which one is off. Then your own figures from past projects help. How to chase missing quotes is covered in the article on tracking supplier quote responses.
Does Scalera flag unusual prices automatically?
Scalera reads incoming quotes and lines them up along your bill of quantities, line by line. Gaps stand out immediately (quote comparison). Which prices are unusual and who gets the contract is your team's decision.
Key takeaways
- Check every line item first, then the total. Low and high prices can cancel out in the total.
- The median per line item is a robust benchmark. You set the review threshold and apply it equally to all.
- An unusual price is a question: misread, different scope, shifted, arithmetic error or genuine advantage.
- Run the numbers on line items with uncertain quantities. A low price can flip the ranking after a quantity change.
- Public clients must clarify abnormally low prices. The same logic helps in private purchasing too.
Next steps
Take your last bid tabulation, work out the median for each line item and flag everything above your threshold. A demo shows how Scalera reads quotes and lines them up.
Disclosure: this guide is published by Scalera. It is not legal advice. The legal texts and the documents of the specific procedure prevail.
Sources
- Germany: Section 60 VgV, abnormally low tenders, gesetze-im-internet.de, accessed 24 Nov 2026
- Germany: Section 15 VOB/A 2019, clarification of tender content, Section 16c VOB/A 2019, examination and Section 16d VOB/A 2019, evaluation, lxgesetze.de, accessed 24 Nov 2026
- Austria: Section 137 BVergG 2018, review of price reasonableness and Section 138 BVergG 2018, in force from 1 Mar 2026, RIS, accessed 24 Nov 2026
- Switzerland: Federal Act on Public Procurement (PPA/BöB), SR 172.056.1, as of 1 Jan 2026, Art. 38 and 39, accessed 24 Nov 2026