Construction tender pricing: how a unit rate is built

A bill of quantities asks for a price per item. Behind it sits the tender estimate: it splits each item into costs and adds markups. If you know how it is built, you price faster, understand queries from the contracting authority and see why every supplier's price ends up inside the unit rate.

Abstract illustration: a bill of quantities item is split into four coloured cost blocks that stack with a markup band into a price column.
Introduction
A unit rate is the direct cost of the item plus markups. Material costs come from supplier quotes. AI speeds up reading, matching and requesting quotes, the pricing decision stays with your team.

3

Forms 221, 222 and 223 set out in the German federal VHB how bidders present their pricing (VHB 2017, 2023 version)

€50,000

Above this estimated bid value, forms 221 to 223 are part of federal tender documents (guidelines on 211)

6 K sheets

K2 to K7 are in Annex A of the Austrian standard ÖNORM B 2061:2020 (Austrian Standards)

€100,000

Above this estimated contract value, the federal client specifies all items for form 223 (guidelines on 223)

In short

  • A unit rate consists of the direct costs of the item (labour, materials, plant, other costs, subcontractors) plus markups for site overheads, general overheads, and risk and profit (German federal VHB, form 221).
  • Markups are either applied as predetermined percentages (form 221) or allocated over the final total (form 222).
  • Public clients can review the pricing: in Germany with forms 221 to 223, in Austria with K sheets under ÖNORM B 2061, and at Swiss federal level through explanations under Art. 38 BöB.
  • AI speeds up reading, matching and requesting quotes. With Scalera, price calculations remain in your ERP or CRM (FAQ).

As of 21 Nov 2026. German federal VHB (2023 reading version), Austrian Standards and the Swiss BöB (as of 1 Jan 2026) checked in the original. Not legal advice.

What is tender pricing in construction?

Tender pricing is the cost estimate for every item in a bill of quantities, done before the bid is submitted. Each item ends with a unit rate, which multiplied by the quantity gives the total price. How unit rates, totals and lump sums relate is explained in the article on price types in a bill of quantities.

The Austrian standard ÖNORM B 2061 puts the purpose briefly: it governs how construction work is priced as the basis of the bid and gives guidance on how to structure the estimate (Austrian Standards, in German). It does not restrict a company's freedom to price as it sees fit (ÖNORM B 2061:2020).

Pricing happens in two places. The contractor prices the bill of quantities for the client. Before that, manufacturers and distributors price their share, namely materials and systems, and so supply one building block of the contractor's estimate.

Which costs make up a unit rate?

A unit rate is made up of the direct costs of the item plus markups. Form 221 of the German federal VHB calls the direct costs immediate production costs and splits them into five cost types (form 221, section 3).

Building blocks of a unit rate under VHB form 221
BlockWhat it coversLine
Labourtotal hours × charge-out wage3.1
Materialsincl. auxiliary materials3.2
Plantincl. energy and fuel3.3
Otherexplained by the bidder3.4
Subcontractwork let to others3.5
Markupssite and general overheads, risk and profit2.1–2.3

Source: German federal VHB 2017, form 221 (pricing with markup calculation), in German.

Site overheads arise for the site as a whole, such as site management, keeping plant on site or site set-up. General overheads carry the business. The forms split risk and profit into profit, company-related risk and work-related risk (forms 221 and 222).

What is the charge-out wage?

The charge-out wage is the hourly rate at which labour enters the unit rates. It starts from the average wage, adds wage-related and ancillary wage costs to get the costing wage, and then adds the labour markup (form 221, lines 1.1 to 1.6). In Austria, the K3 sheet covers the personnel rate (Austrian Standards).

Markup calculation or allocation over the final total?

Both methods lead to the unit rate, they just spread the overheads differently. In markup calculation you work with predetermined percentages per cost type, for example a fixed markup on materials (form 221).

When allocating over the final total, you calculate the site overheads for the specific project as amounts. Together with general overheads, risk and profit, you spread them over the direct costs as an allocation (form 222).

For German federal tenders you submit one of the two forms, depending on how your company prices. The list of documents asks for pricing details in line with form 221 or 222 (form 216).

How does a supplier price affect the unit rate?

Through the material costs. The price in the distributor's or manufacturer's quote is the starting value for the materials line, and the markup goes on top. A fictitious example with markup calculation shows this for one square metre of an interior wall in sand-lime brick.

Fictitious worked example: 1 m² interior wall
BlockCalculation€/m²
Labour0.9 h × €68.0061.20
Materials€32.00 + 18%37.76
Plant€2.50 + 18%2.95
Unit rateTotal101.91

All values fictitious for illustration. Charge-out wage including labour markup; 18% markup on materials and plant.

If the distributor offers the bricks and mortar 10% cheaper, at €28.80, the materials line drops to €33.98. The unit rate falls to €98.13 per m², about 3.7% lower. On large quantities, this difference can change the ranking in the bid comparison.

Conversely, a quote in a different unit can raise the price unnoticed. If the distributor prices per piece or pallet, the estimate first has to be converted to m² (converting units of measure). Discounts, early-payment terms and freight also need to be made comparable before a quote enters the materials line (terms in bid comparison).

“Your supplier's price doesn't sit next to the unit rate, it sits inside it, with a markup.”

When do you have to disclose your pricing?

When a public client checks whether prices are reasonable. Germany, Austria and Switzerland handle this differently.

Disclosure of pricing compared
CountryBasisWhat is requested
GermanyFederal VHB 2017Form 221 or 222, on request 223
AustriaÖNORM B 2061:2020Parts of the pricing in K sheets
SwitzerlandBöB, Art. 38Explanation of the bid

Sources: VHB, guidelines on 211 and 223, form 216; Austrian Standards, K sheets; BöB (SR 172.056.1), as of 1 Jan 2026 (all in German).

Germany: forms 221 to 223

For federal projects, forms 221 to 223 are attached to the tender documents when the estimated bid value is more than €50,000. They can be omitted if the original estimate is requested instead (guidelines on 211, no. 1).

Form 223 breaks individual unit rates down into labour, materials, plant and other costs. Above €50,000 the client specifies the price-determining items, above €100,000 all items. It is only requested from bidders on the shortlist, and the details are confidential (guidelines on 223).

Austria: K sheets under ÖNORM B 2061

To review bids, the client can ask for parts of the pricing to be submitted, using the costing forms. The current edition of ÖNORM B 2061 dates from 1 May 2020, and the K sheets K2 to K7 are in its Annex A (Austrian Standards).

Switzerland: explanations under the BöB

In federal procurement, the contracting authority can ask bidders to explain their bids. If a total price appears unusually low compared with other bids, it must make appropriate enquiries as to whether the conditions for participation are met and the requirements were understood (Art. 38 para. 2 and 3 BöB).

Why does the estimate still matter after the award?

Because variations build on it. If a contractor on a German federal project claims additional payment, it has to show that the new price is based on the pricing of the contract. It submits the calculation in line with form 223 where possible (federal VHB, guideline 510, no. 3.2.1).

Austria follows the same principle: new prices for changes in the work are derived from the contract price basis, and the K sheets disclose that basis (Austrian Standards). A clean split into labour, materials and markups therefore saves you discussions later.

What does this mean for manufacturers and distributors?

For the contractor, your quote is one figure in the materials line. If it arrives quickly and in a comparable form, the estimator can price directly with your product.

  • Answer per bill of quantities item, not per catalogue page. That way the estimator can assign your price directly to the item (AVA and supplier quotes).
  • State unit, discount, freight and validity clearly so your price goes into the estimate without queries (terms).
  • Offer complete systems, including accessories. Otherwise missing parts can show up as a variation or a risk markup (accessories in quotes).
  • For your own configuration and pricing logic on system products, see CPQ or AI.

Where does AI help and where does the estimator decide?

AI helps with the groundwork, the pricing decision stays with people. The groundwork is everything that happens before the first markup: reading the bill of quantities, structuring items, matching products and suppliers, sending requests and comparing quotes.

  • For manufacturers and distributors, Scalera extracts items from tenders and matches products from your own catalogue, with rationale and AI confidence (Product Matching).
  • For contractors, processors and distributors, Scalera assigns bill of quantities items to suitable suppliers or subcontractors, creates ready-to-send requests and tracks responses (Supplier Matching; tracking responses).
  • Scalera reads incoming quotes and lines them up item by item in a bid comparison (Quote comparison).

You set time allowances, markup rates and risk yourself. According to the Scalera FAQ, price calculations remain in your ERP or CRM system (FAQ).

The same pattern shows internationally. At US general contractor Hensel Phelps, estimators in an AI pilot check every output against the source documents and keep the final call on scope and pricing (Neuron Factory press release, 16 Nov 2026). According to industry research by Bluebeam, only 28% of architecture, engineering and construction firms have moved AI into production (Bluebeam, 10 Nov 2026).

How do you set up a fast pricing workflow?

  1. Import the bill of quantities and structure the items, whatever the format (GAEB, PDF, Excel).
  2. Assign materials and subcontractors per item and send price requests with the same item overview (automating price requests).
  3. Make quotes comparable in the bid comparison: unit, discount, early-payment terms, freight.
  4. Enter direct costs and markups in your estimating software, according to your method (predetermined markups or allocation over the final total).
  5. Check plausibility: labour, materials, plant and other costs must add up to the unit rate for each item, as form 223 requires.

The last step follows the logic of form 223: there, the unit rate offered is the sum of the columns for labour, materials, plant and other costs (form 223, column 10). If you check this way, you are already prepared for a later breakdown.

Frequently asked questions

What is the difference between the costing wage and the charge-out wage?

The costing wage (Kalkulationslohn) is the average wage plus wage-related costs and ancillary wage costs. The charge-out wage (Verrechnungslohn) adds the markup on labour and is the rate that goes into the unit rates (form 221, lines 1.1 to 1.6).

What is the original estimate (Urkalkulation)?

The original estimate is the bidder's own pricing documents. Under the German federal VHB, the contracting authority can ask for it instead of forms 221 to 223. It is opened to check the prices and then sealed again (guidelines on 211 and form 216).

Does every bidder have to submit form 223?

No. Under the federal VHB it is only requested from bidders on the shortlist, and the information must be treated as confidential. Above €50,000 the client specifies the price-determining items, above €100,000 all items (guidelines on 223).

What are K sheets?

K sheets are the costing forms of the Austrian standard ÖNORM B 2061:2020: K2 total markups, K3 personnel rate, K4 material prices, K5 composite price components, K6 plant prices and K7 presentation of the pricing (Austrian Standards, K sheets, in German).

Do the VHB forms also apply to private clients?

The VHB is the handbook for federal construction projects in Germany and implements parts A and B of the VOB (fib-bund.de, in German). Whether another client asks for pricing details is stated in its tender documents.

Can AI take over tender pricing completely?

Not with Scalera. The AI reads bills of quantities, matches items to products or suppliers and prepares requests and bid comparisons. According to the Scalera FAQ, price calculations remain in your ERP or CRM system (FAQ).

How do Scalera results get into my estimating software?

You export the matched items as CSV, XML or GAEB, or by API, into your ERP, CPQ or CRM system (Product Matching). For ERP systems there are interfaces in SAP IDoc format, a REST API and configurable custom formats (FAQ, ERP integrations).

Key takeaways

  • A unit rate is direct costs plus markups. Separating the building blocks lets you explain every item.
  • Supplier prices enter the unit rate through material costs, with a markup. Units and terms need to be comparable first.
  • Public clients in Germany, Austria and Switzerland can review your pricing, each under their own rules.
  • The estimate still matters after the award, because variations build on it.
  • AI handles the groundwork from the bill of quantities to the bid comparison. A demo shows what that looks like for you.

Disclosure: This article is published by Scalera and is not legal advice. The tender documents in each case, the German federal VHB in its current version, ÖNORM B 2061 and the Swiss BöB are authoritative.

Sources

  1. German federal procurement and contract handbook for construction (VHB), VHB 2017, reading version as of 2023: forms 216, 221, 222, 223, guidelines on 211 and 223, guideline 510; overview on fib-bund.de (in German), accessed 21 Nov 2026
  2. Austrian Standards, K sheets and ÖNORM B 2061:2020-05-01 (in German), accessed 21 Nov 2026
  3. Swiss Federal Act on Public Procurement (BöB), SR 172.056.1, as of 1 January 2026, Art. 38 (in German), accessed 21 Nov 2026
  4. Neuron Factory, press release of 16 Nov 2026, and Bluebeam, press release of 10 Nov 2026, accessed 21 Nov 2026
  5. Scalera, Product Matching, Supplier Matching, Quote comparison and FAQ, accessed 21 Nov 2026
  6. Interior wall worked example: fictitious for illustration