In short
- An award recommendation turns the review and the bid tabulation into one proposal: which bidder, at what price, for what reasons.
- Planners prepare it as part of stage 7 (HOAI stage 7); purchasing and estimating at a general contractor prepare it for subcontractors and suppliers.
- Public buyers also have to document the procedure (Section 8 VgV, Section 147 BVergG 2018) and keep the records (Art. 49 BöB).
- The template below has nine parts. Only the recommendation, the reasons and the open points belong on the first page.
As of 25 Nov 2026. Legal texts checked on gesetze-im-internet.de, ris.bka.gv.at and fedlex.admin.ch. Not legal advice.
What is an award recommendation?
An award recommendation is the written proposal of which bidder should get a contract, with the price and the reasons. It comes at the end of the bid review and goes to the person who actually places the contract.
The German fee scale HOAI calls it a Vergabevorschlag. Among the eight basic services of stage 7 it lists «preparing the award recommendations, documenting the award procedure», right after the bid tabulation and bidder meetings (HOAI Annex 10, stage 7). How planners use AVA software in this stage is covered in the article on AVA software.
Who writes it and who decides?
1
Planner for the client
Reviews the bids, builds the bid tabulation and writes the recommendation (stage 7 c to e).
Decides: the client
2
Purchasing at the general contractor
Compares quotes from subcontractors and suppliers and proposes the award per trade or lot.
Decides: project or executive management
3
Public contracting authority
Records the reasons for selection and rejection in the award record (Section 8 VgV).
Decides: the public buyer
The same separation applies in all three cases: whoever recommends does not decide. The recommendation therefore has to be written so that someone without the details can follow it or consciously disagree.
What goes into an award recommendation?
The template below has nine parts. The first three fit on one page and are enough for the decision; the rest is the evidence.
- Recommendation: bidder, trade or lot, recommended contract value net, date.
- Reasons: two to four sentences on why this bid comes first under the criteria set beforehand.
- Open points: reservations, conditions or clarifications to settle before the contract.
- Scope and budget: what is being awarded and how the price compares with the budget or cost estimate.
- Procedure: who was asked, the deadline, how many quotes came in.
- Review: formal, arithmetic and technical review of each bid, with the result.
- Ranking: all scored bids with comparison total and a short remark.
- Clarification: which questions were asked, which answers came back, what follows from them.
- Appendix: bid tabulation, minutes, scoring matrix, bids.
A made-up example of the first three parts: «We recommend awarding lot 4 ventilation to bidder B for €412,000 net. B ranks first on price and quality and is the only bidder meeting all minimum requirements without deviation. Still open is written confirmation of the delivery date for the air handling units by 5 December.» The first page needs nothing more.
How does a bid tabulation become a recommendation?
The bid tabulation shows numbers; the recommendation answers questions. The table maps the usual questions from decision makers to the part that answers them.
| Question | Answered in | Evidence |
|---|---|---|
| Who and how much? | Recommendation | Ranking |
| Why not the cheapest? | Reasons | Scoring matrix |
| Within budget? | Scope and budget | Cost estimate |
| Are the prices reliable? | Review, clarification | Bid tabulation, minutes |
| What can still go wrong? | Open points | Correspondence |
Mapping by Scalera. Parts as in the template above.
Before you write a ranking, put all quotes on the same basis: arithmetic errors corrected, discounts, early payment discounts and freight treated the same way, missing items visible. The article on discounts and freight covers terms; unusual unit prices are covered in the guide on reviewing a bid tabulation.
How do you justify the recommendation so it holds up?
Justify it with the criteria set before the request and communicated to bidders, not with new ones. How price and quality are weighted is explained in the article on award criteria. If the recommended bid is not the lowest price, name the reason precisely: which requirement, which deviation, which amount.
Also record why the other bids were not chosen. You will need these reasons later for the rejection and, in public procurement, for the notice to bidders.
An award recommendation is good when someone who was not involved can follow the decision in five minutes.
- Describe deviations with item and amount, not as an impression.
- Score alternative bids separately from the main bid and label them as such. The terms are explained in the glossary on main and alternative bids.
- Minute bidder meetings and clarifications with date and result and file them in the appendix.
- If fewer quotes came in than requested, state the number and the reasons where known.
What do public buyers in DE, AT and CH require?
In public procurement two duties come on top of the recommendation: documenting the procedure and informing bidders about the decision. In Germany the rules below apply to contracts at or above the EU thresholds (Section 106 GWB, Section 1 VgV), and to works contracts via Section 2 VgV.
| Country | Documentation | Notice |
|---|---|---|
| Germany | Award record with 12 items, kept at least 3 years (Section 8 VgV) | Rejection with reasons, contract after 15 or 10 days (Section 134 GWB) |
| Austria | Award record for every contract awarded (Section 147 BVergG 2018) | Notice with reasons, standstill 10 or 15 days (Section 143 BVergG 2018, Section 144 BVergG 2018) |
| Switzerland (federal) | Documents kept at least 3 years (Art. 49 BöB) | Summary reasons for the award, 20-day appeal period (Art. 51, 56 BöB) |
As of 25 Nov 2026. Switzerland: only federal law reviewed (BöB, as of 1 Jan 2026).
Several mandatory items of the German award record are already in the template above: scope and value, accepted and rejected bidders with reasons, reasons for rejecting abnormally low bids, the name of the winning bidder with reasons (Section 8(2) nos. 1 to 5 VgV). A well written recommendation is therefore the groundwork for the record.
In Austria the standstill period and notice are not a formality: an award before the period ends is absolutely void (Section 144(1) BVergG 2018).
What applies when you award privately as a general contractor?
When you award work to subcontractors or suppliers as a general contractor, these duties do not apply directly. Management asks the same questions, though: who, why, what is open. A fixed structure saves follow-up questions and makes awards comparable across projects.
- Define who approves above which amount, and write the approval into the recommendation.
- Use the same template for all trades, including small lots.
- Tell unsuccessful bidders promptly, with a factual reason, instead of leaving them waiting.
- If quotes are missing, follow up before you recommend. The article on tracking supplier quote responses shows how to do that without phone calls.
What does this mean for manufacturers and distributors?
Your quote ends up in someone else's award recommendation. The easier it is to place there, the less anyone has to query it or note a reservation.
- Price every item or state clearly which ones you do not offer.
- Label third-party products and alternatives as such instead of mixing them into the main item.
- Answer clarification questions in writing and before the deadline.
- Write your terms so they can be transferred into a bid tabulation.
If you are rejected, use it as information. In public procurement you are entitled to the reasons: in Germany through the notice under Section 134 GWB, in Austria together with the total price and the characteristics and advantages of the winning bid (Section 143 BVergG 2018).
What Scalera prepares and what stays with you
A recommendation starts with a complete bid tabulation. In Quote comparison Scalera builds it from the incoming quotes: no retyping, gaps show up at once, and a dashboard shows who has replied and who is still missing. If a quote does not arrive, Scalera sends a reminder automatically.
Suitable manufacturers or subcontractors are requested beforehand through Supplier matching, per bill of quantities item. Your team decides on the award, and the recommendation with its reasons remains your document.
Frequently asked questions
What is the difference between an award recommendation and an award record?
The award recommendation proposes who should get the contract and goes to the person who decides. For public buyers, the award record documents how the whole procedure ran (Section 8 VgV, Section 147 BVergG 2018). The recommendation is one building block the record later draws on.
Who decides on the award?
Whoever places the contract: the client, at a general contractor the project or executive management, and in public procurement the contracting authority. Under HOAI Annex 10 planners assist with the award and prepare the recommendation; they do not make the decision.
How long do the documents have to be kept?
Public buyers in Germany keep them until the contract ends, and for at least three years from the award (Section 8(4) VgV). Swiss federal buyers keep them for at least three years from the legally binding award (Art. 49 BöB). In private purchasing you set the period yourself, ideally in line with the warranty period of your contract.
When can the contract be signed after the award decision?
In Germany at the earliest 15 calendar days after the notice is sent, or 10 if it is sent electronically (Section 134 GWB). In Austria after the standstill period of 10 or 15 days (Section 144 BVergG 2018). At Swiss federal level, for contracts under international agreements only after the 20-day appeal period, otherwise once the award has been made (Art. 42 and 56 BöB).
What do I learn as a bidder when I am rejected?
In Germany the name of the winning bidder, the reasons your bid was not accepted and the earliest contract date (Section 134 GWB). Austria also gives the total price and the characteristics and advantages of the winning bid (Section 143 BVergG 2018). At Swiss federal level the summary reasons for the award state the procedure, the name, the total price and the characteristics and advantages of the winning bid (Art. 51(3) BöB).
What goes into the appendix instead of the recommendation?
The full bid tabulation, the minutes of clarifications and bidder meetings, the scoring matrix and the bids themselves. The recommendation only refers to them. How a line-by-line bid tabulation is built is explained in the bid comparison guide.
Does Scalera write the award recommendation?
No. Scalera does the groundwork and delivers a complete basis with the bid tabulation (Quote comparison). Reasons, recommendation and award stay with your team.
Key takeaways
- An award recommendation answers on one page: who, why, what is open. The rest is appendix.
- Justify only with criteria set beforehand and state deviations with item and amount.
- Record the reasons against the other bids. You need them for the rejection and the bidder notice.
- Public buyers also document the procedure in an award record and inform bidders before the contract.
- As a supplier you make the recommender's job easy: complete, clearly labelled, in writing, on time.
Next steps
Copy the nine parts into your next award and check whether the first page is clear without the appendix. To see how Scalera reads quotes and builds the bid tabulation, book a demo.
Disclosure: Scalera is the publisher of this guide. The example is made up. The legal texts and tender documents govern your procedure; this text is not legal advice.
Sources
- Germany: HOAI, Annex 10 (buildings and interiors), stage 7, gesetze-im-internet.de, accessed 25 Nov 2026
- Germany: Section 1 VgV, Section 2 VgV and Section 8 VgV, documentation and award record, gesetze-im-internet.de, accessed 25 Nov 2026
- Germany: Section 106 GWB, thresholds and Section 134 GWB, duty to inform and standstill, gesetze-im-internet.de, accessed 25 Nov 2026
- Austria: Section 143 BVergG 2018, Section 144 BVergG 2018 and Section 147 BVergG 2018, each in force from 1 Mar 2026, RIS, accessed 25 Nov 2026
- Switzerland: Federal Act on Public Procurement (BöB), SR 172.056.1, as of 1 Jan 2026, Art. 42, 49, 51 and 56, accessed 25 Nov 2026
- Scalera, Quote comparison and Supplier matching, accessed 25 Nov 2026